| # | Deliverable / Milestone | Owner | Start | Target | % Done | Status |
|---|---|---|---|---|---|---|
| 1. | Phase 1: Align / Planning | ZenAtikin / TxDOT | 4/07/26 | 4/24/26 | 100% |
Complete |
| 2. | Project Schedule & Organization | Vendor PM / TxDOT PM | 4/07/26 | 4/17/26 | 100% |
Complete |
| 3. | AI Review Board Approval | Vendor PM / TxDOT PM | 4/30/26 | 5/01/26 | 100% |
Complete |
| 4. | Phase 2: Solution Discovery & Design / SRD | ZenAtikin / TxDOT | 4/14/26 | 6/26/26 | 78% |
In Progress |
| 5. | Proof of Concept (PoC) Build & Walkthrough | ZenAtikin SA | 6/01/26 | 6/04/26 | 65% |
In Progress |
| 6. | ARB3 | TxDOT TPO / ARB | 6/01/26 | 6/05/26 | 0% |
Not Started |
| 7. | ATO Preparation | TxDOT TPO / InfoSec | 4/14/26 | 6/26/26 | 10% |
In Progress |
| 9. | Phase 3: Build & QA | ZenAtikin SA / Dev | 5/25/26 | 7/10/26 | 5% |
In Progress |
| 10. | Phase 4: UAT & System Acceptance | ZenAtikin / TxDOT | 6/29/26 | 7/09/26 | 0% |
Not Started |
| 11. | Pre-CAB & CAB Meeting | TxDOT PM / TPO | 6/08/26 | 7/03/26 | 0% |
Not Started |
| 12. | Phase 5: Go-Live | ZenAtikin / TxDOT | 7/10/26 | 7/10/26 | 0% |
Not Started |
| 13. | Hypercare | ZenAtikin / TxDOT | 7/10/26 | 8/14/26 | 0% |
Not Started |
| 14. | Project Closure Activities | Paula Perreira | 8/17/26 | 9/30/26 | 0% |
Not Started |