| # | Deliverable / Milestone | Owner | Start | Target | % Done | Status |
|---|---|---|---|---|---|---|
| 1. | Phase 1: Gap Analysis & Solution Alignment | TxDOT / Delasoft | 4/01/26 | 5/30/26 | 70% |
In Progress |
| 2. | End-to-End Project Schedule Finalized | TxDOT PM | 4/15/26 | 5/15/26 | 99% |
In Progress |
| 3. | District Workflow & Intake Form Approval | TPD | 4/08/26 | 6/05/26 | 99% |
In Progress |
| 4. | Requirements / User Stories / Data Dictionary | Delasoft / TxDOT | 4/07/26 | 6/30/26 | 60% |
In Progress |
| 5. | Phase 1 Project Documentation (17 Docs) | TxDOT PM | 4/01/26 | 6/01/26 | 50% |
In Progress |
| 6. | Technical Specifications & Traceability | Delasoft | 6/08/26 | 6/30/26 | 20% |
In Progress |
| 7. | Phase 2: Configuration & Build | Delasoft | 6/09/26 | 9/25/26 | 0% |
Not Started |
| 8. | Phase 3: Testing & Pilot | TxDOT / Delasoft | 8/31/26 | 11/20/26 | 0% |
Not Started |
| 9. | Phase 4: Go-Live Preparation | TxDOT / Delasoft | 10/20/26 | 1/29/27 | 0% |
Not Started |
| 10. | Go-Live | TxDOT / Delasoft | 1/29/26 | 1/29/26 | 0% |
Not Started |
| 11. | Phase 5: Migrate First 10 Districts | TxDOT / Delasoft | 1/29/27 | 3/15/27 | 0% |
Not Started |
| 12. | HyperCare & Closeout | Delasoft | 2/16/27 | 4/30/27 | 0% |
Not Started |