Enterprise Driveway Access Permit (EDAP)  ·  Stakeholder Status Update
May 20, 2026
OVERALL STATUS
Project Status: ON TRACK
TPD delivered workflows, standardized intake form and roles on May 18th.

Requirements sessions in progress and expected to finish first week of June. User stories and data dictionary in process and expected finish June 5th.

Detailed specifications for formal review and sign-off are expected 2nd week of June with a 10-day review/approval period.

End-to-end full project schedule & WBS draft complete and will be reviewed in the May 27th weekly meeting.

Phase 1 Discovery, Design, and Planning project documentation are 8 of 17 complete and on track for end of month.
MAJOR ACTIVITIES
✔  COMPLETED
Program Management
• End-to-end full project schedule & WBS draft completed (5/20)
• 8 of 17 Phase 1 project documents completed
Requirements
• TPD delivered district workflows, standardized intake form & roles (5/18)
Interface Integration
• Interface deep dives completed: MuleSoft, ArcGIS, DocuSign, OnBase, Bluebeam, Snowflake
▶  UPCOMING
Program Management
• Finalize end-to-end schedule (99%)
• Deliver all 17 Phase 1 docs (50%)
Requirements
• Complete user stories/rules (60%)
• Tech specs sign-off
Platform & Security
• Early Delasoft platform readiness
• Security requirements assessment
Interface Integration
• Determine if MuleSoft is necessary for each interface.
• ArcGIS, DocuSign, OnBase (Async), Bluebeam, Snowflake occurring the week of May 18th
MAJOR MILESTONES
# Deliverable / Milestone Owner Start Target % Done Status
1. Phase 1: Gap Analysis & Solution Alignment TxDOT / Delasoft 4/01/26 5/30/26
70%
In Progress
2. End-to-End Project Schedule Finalized TxDOT PM 4/15/26 5/15/26
99%
In Progress
3. District Workflow & Intake Form Approval TPD 4/08/26 6/05/26
99%
In Progress
4. Requirements / User Stories / Data Dictionary Delasoft / TxDOT 4/07/26 6/30/26
60%
In Progress
5. Phase 1 Project Documentation (17 Docs) TxDOT PM 4/01/26 6/01/26
50%
In Progress
6. Technical Specifications & Traceability Delasoft 6/08/26 6/30/26
20%
In Progress
7. Phase 2: Configuration & Build Delasoft 6/09/26 9/25/26
0%
Not Started
8. Phase 3: Testing & Pilot TxDOT / Delasoft 8/31/26 11/20/26
0%
Not Started
9. Phase 4: Go-Live Preparation TxDOT / Delasoft 10/20/26 1/29/27
0%
Not Started
10. Go-Live TxDOT / Delasoft 1/29/26 1/29/26
0%
Not Started
11. Phase 5: Migrate First 10 Districts TxDOT / Delasoft 1/29/27 3/15/27
0%
Not Started
12. HyperCare & Closeout Delasoft 2/16/27 4/30/27
0%
Not Started
INDICATORS: On Track / In Progress At Risk Off Track Not Started Complete
RAID: Risks · Actions · Issues · Decisions
⚠ Risks
OnBase code freeze through Oct–Dec 2026 (OB Upgrade / Cloud Migration) may impact integration timeline and EDAP project scheduling decisions.
✔ Actions
Met with OnBase team May 18th to decide timing of EDAP work relative to OnBase code freeze.
⚑ Issues
No active issues recorded.
✦ Decisions
OnBase is used for archiving. OnBase and EDAP teams will meet late Sept 2026 to plan the necessary work to meet go live.