| # | Deliverable / Milestone | Owner | Start | Target | % Done | Status |
|---|---|---|---|---|---|---|
| 1. | Teams Channel & SharePoint Site | Paula Perreira | 4/30/26 | 5/18/26 | 100% |
Complete |
| 2. | Develop Pilot Process, Metrics & Surveys | Paula Perreira | 5/04/26 | 5/29/26 | 50% |
In Progress |
| 3. | PING / MFA | Jahnavi Mattaparti | 5/07/26 | 5/18/26 | 100% |
Complete |
| 4. | ID Pilot Members | Paula Perreira | 4/30/26 | 5/18/26 | 50% |
In Progress |
| 5. | Provisioning | Q. Khan & J. Rucker | 5/19/26 | 5/22/26 | 100% |
Complete |
| 6. | Security Exception | Jahnavi Mattaparti | 5/12/26 | 5/29/26 | 0% |
Not Started |
| 7. | Pilot + Support | Team | 6/01/26 | 8/24/26 | 0% |
Not Started |
| 8. | Post Pilot Analysis | Paula Perreira | 8/25/26 | 9/18/26 | 0% |
Not Started |
| 9. | Project Close | Paula Perreira | 9/21/26 | 9/30/26 | 0% |
Not Started |